J.M. CALDWELL SR. COMMUNITY PARK
PHASE 1
Project: Four artificial turf baseball/softball fields
The Caldwell Park bond projects represent a major investment in expanding and improving one of Princeton’s most popular community destinations. Funded through the voter-approved bond program, these enhancements will transform Caldwell Park into a more vibrant and versatile recreation area. Planned improvements include upgraded sports fields, expanded parking, new restroom facilities, enhanced lighting, and improved accessibility throughout the park.
Funding Source: 2023 Parks Bond
Project Status: Completed
PHASE 2
Project: Three turf multipurpose fields
Funding Source: 2023 Parks Bond
Recent Updates:
-
Construction began on February 23, 2026.
-
The Council approved new energy-efficient LED field lighting to improve safety, visibility, and extended use of athletic fields. In addition, three new synthetic turf multipurpose fields will be constructed to expand year-round recreation opportunities for the community.
Funding Source: 2023 Parks Bond
PHASE 3
Project: Playground and courts upgrades
Funding Source: 2023 Parks Bond
Timeline: Potential construction start date Fall 2026.
Highlights:
-
83 acres
-
Playgrounds
-
Multi-Use Sports Fields
-
Pickleball Courts
-
Sand Volleyball Courts
-
1-Mile Walking Loop
-
Basketball Courts
-
Baseball Fields
-
Softball Field
-
Event Plaza/Lawn
-
Restrooms/Concessions

PHASE 1

PHASE 2